West Suffolk Council needs to find £1.67 million for 2027/28 after losing a £1.1m government grant. Its plans still assume a 3% council tax rise.

West Suffolk Council has to find £1.67 million to balance its budget for 2027/28. Most of the gap comes from losing a £1.1 million government grant.

The figures are in a report to the council’s Performance and Audit Scrutiny Committee on Thursday 26 November (West Suffolk Council, report PAS/WS/26/023). The report says a balanced budget is still “considered deliverable”, as long as no further pressures appear. It goes to Cabinet on 8 December.

Overview

  • The gap: £1.67 million for 2027/28, in a budget that was balanced in principle in February.
  • The main cause: the government’s Adjustment Support Grant, about £1.1 million, is only being paid for 2026/27.
  • Later years: without new savings, the gap grows to £4.33 million by 2030/31.
  • Council tax: the plans assume a 3% rise in the council’s share. Nothing is decided until 23 February 2027.

Where the £1.67 million comes from

The council’s list of budget changes puts a figure on each pressure for 2027/28. The biggest are:

Pressure 2027/28
Removal of the government’s support grant £1.08m
Staff pay award assumed at 3% rather than 2% £0.42m
Empty council properties: lost rent and extra business rates £0.30m
Fuel costs £0.16m
ICT contracts, including Microsoft £0.16m
Electricity £0.13m
Car park business rates after the 2026 revaluation, now under appeal £0.11m
Hiring vehicles to cover bin lorry downtime £0.10m

Some changes help. The council expects these to bring in more or cost less:

  • planning fees: £200,000 more than budgeted
  • solar canopies at the Mildenhall Hub and plant savings at West Suffolk House: £150,000
  • trade waste recycling: £140,000 more
  • the council’s solar farm and Solar for Business scheme: £110,000 more
  • food waste: £100,000 less in tipping costs

Each extra 1% on the staff pay award would cost about £400,000 a year, the report says. The 2026 pay award, agreed nationally, was 3.3%.

The grant Suffolk’s councils want back

The Adjustment Support Grant is being paid only in 2026/27, not across the full three-year funding settlement to 2029. All of Suffolk’s councils have written jointly to the government asking for it to continue (West Suffolk Council).

Cllr Diane Hind, the cabinet member for resources, said: “These new pressures are beyond West Suffolk Council’s control.” She added that the council was “reviewing costs and income, finding more efficient ways of working”.

How the council plans to close the gap

The report lists the areas under review, rather than specific cuts. They include:

  • a review of every fee and charge, so that users pay the cost of a service “rather than being subsidised through the tax base”
  • more trade waste business
  • rents and leases on the council’s non-operational property, and possible sales of buildings
  • higher contributions from its companies, Verse and Barley Homes
  • handing more community assets to town and parish councils, trusts and charities
  • the big service contracts, and how they are bought

Firm savings will be reported back on 28 January 2027.

The bigger picture

The council holds £6.13 million in its general reserve, of which £5.0 million is uncommitted. Its earmarked reserves are forecast at £45.2 million at the end of 2026/27. Under the current budget they fall to £30.4 million by 2030, mostly through spending on building projects.

Without new savings, the gap grows each year:

Year Gap before new savings
2027/28 £1.67m
2028/29 £2.63m
2029/30 £3.60m
2030/31 £4.33m
Bar chart of West Suffolk Council's budget gap before new savings: £1.67 million in 2027/28, £2.63 million in 2028/29, £3.60 million in 2029/30 and £4.33 million in 2030/31.
Chart by The Bury St Edmunds Post, from West Suffolk Council's report of 26 November 2026.
Share this chartFacebookWhatsAppX

The report sets these later years “in the context of” local government reorganisation from April 2029.

What it means for you

The council’s share of a band D bill in Bury St Edmunds is £209.70 this year, out of £2,288.88 in total (see our council tax bands page). A 3% rise, the figure the plans assume, would add about £6.29 a year to that share at band D. That is our calculation, and the decision is not made until February.

Fees and charges are the change most residents are likely to notice. The report does not say which charges will rise.

The timetable:

  • 8 December: Cabinet considers the proposals.
  • 28 January 2027: update to the scrutiny committee, with savings and reserves.
  • 9 February 2027: Cabinet’s budget and council tax report.
  • 23 February 2027: full council sets the budget and council tax.

The report also notes the £100 Household Energy Payment announced in the Autumn Budget. In West Suffolk it will be paid through Anglia Revenues Partnership from January 2027, with details still to come from the government.